Bisha Mine | Overview

Project Overview

Bisha is a large precious and base metal-rich volcanogenic massive sulphide (VMS) deposit located 150km west of Asmara, Eritrea, East Africa. Deposit mineralization consists of gold and silver oxides, in addition to copper and zinc massive sulphides. The project benefits from the strong support of the Government of Eritrea and good local road and port infrastructure.

The Bisha Mine began construction in September 2008 and declared commercial production in February 2011. The mine is a low-cost gold producer for the first two years, and a high-grade copper concentrate and zinc producer for the remaining mine life. View Resource and Reserves.

After depletion from 2011, the estimated remaining payable production from the Bisha mine is 330,000 ounces of gold, 10,300,000 ounces of silver, 860,000,000 pounds of copper and 1,890,000,000 pounds of zinc.

Licensed Areas

Bisha's mining and exploration licenses cover a contiguous area of 86 km2. The Bisha Mine and North West zone are both located within the 16.5 km2 Bisha mining license and the Harena satellite deposit lies in a separate 7.5km2 mining license. The North West zone has yet to be drilled for resource (underway) and several other geophysical anomalies that have yet to be tested on the licenses.

The State of Eritrea has a free carried 10% interest plus an additional 30% paid participating interest for a total of 40% interest in Bisha. The interest will be paid over time, out of Bisha cash distributions. For more information see our most recent Financial Statements and MD&A.

Commercial Production Schedule

Per July 2012 resource and reserve news release the payable production profile is as follows:

Years

2012 (1)

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

 

Oxide Phase

Supergene Phase

Supergene & Primary Overlap(3)

Primary Phase (2)

Gold

146,000 oz

36,000 oz

32,000 oz

121,000 oz

Silver

221,000 oz

1,600,000 oz

1,560,000 oz

6,940,000 oz

Copper

 

317 Mlbs

242 Mlbs

301 Mlbs

Zinc

 

 

146 Mlbs

1,740 Mlbs

  • (1) From May 31, 2012. Total gold production in 2012 is forecast at 280,000 to 300,000 ounces including Harena oxides. It is anticipated that the Oxide Phase will extend through Q1 2013, when the gold plant will be shutdown to commence supergene phase commissioning.
  • (2) Includes Harena sulphides.
  • (3) The mine plan for the purposes of reserves determination contemplates a period of co-processing supergene and primary ores but Bisha has not made a final determination on this approach. Bisha will continue to evaluate and will advise if and when the approach is adopted.

Note: table above is payable production over the time period indicated. Bisha supergene copper phase is in construction and copper concentrate production is expected in mid-2013.

Bisha Mine Project Milestones

8 years from Discovery to Production

January 2003 Discovery
October 2006 Feasibility Study
December 2006 Social and Environmental Impact Assessment
June 2007 EPCM contractor selected (SENET), engineering commenced
October 2007 State participation agreed (10% free carried + 30% interest to be purchased at fair value by Eritrean National Mining Company
December 2007 Mining and stabilization agreements completed with Eritrean Government
January 2008 Mining license granted
February 2008 Orders placed for critical equipment
August 2008 SENET mobilized to site and site clearing and heavy earth moving started
December 2009 Mills delivered
March 2010 Ball and Sag Mill assembled and set in place
Pre-Strip mining commenced
April 2010 Installation of the liner in the tailings management facility commenced
June 2010 Completion of structural steel and plate-work
October 2010 Plant Commissioning initiated, Power Plant commissioned
December 2010 First Gold Pour
February 2011 Commercial Production Declared; on time and under budget