Milestones
8 years from Discovery to Production
| January 2003 | Discovery |
| October 2006 | Feasibility Study |
| December 2006 | Social and Environmental Impact Assessment |
| January 2007 | Tendering process for EPCM contractor |
| June 2007 | EPCM contractor selected (SENET), engineering commenced |
| October 2007 | State participation agreed (10% free carried + 30% interest to be purchased at fair value by Eritrean National Mining Company |
| December 2007 | Mining and stabilization agreements completed with Eritrean Government |
| January 2008 | Mining license granted |
| February 2008 | Orders placed for critical equipment |
| August 2008 | SENET mobilized to site and site clearing and heavy earth moving started |
| September 2008 - present | Active mine construction |
| July 2009 | $235 Million Debt Financing |
| December 2009 | Mills delivered |
| February 2010 | Debt replaced by Equity Construction 50% complete |
| March 2010 | Ball and Sag Mill assembled and set in place Pre-Strip mining commenced |
| April 2010 | Installation of the liner in the tailings management facility commenced |
| May 2010 | Installation of Ball and SAG mills |
| June 2010 | Completion of structural steel and plate-work |
Future Milestones
Completion of plant electrical and piping
Installation of the electrical power plant
Commencement of ore extraction and stockpiling
Completion of the tailings management facility
Plant commissioning
First gold pour