Milestones
8 years from Discovery to Production
| January 2003 | Discovery |
| October 2006 | Feasibility Study |
| December 2006 | Social and Enviromental Impact Assessment |
| January 2007 | Tendering process for EPCM contractor |
| June 2007 | EPCM contractor selected (SENET), engineering commenced |
| October 2007 | State participation agreed (10% free carried + 30% interest to be purchased at fair value by Eritrean National Mining Company |
| December 2007 | Mining and stabilization agreements completed with Eritrean Government |
| January 2008 | Mining license granted |
| February 2008 | Orders placed for critical equipment |
| August 2008 | SENET mobilized to site and site clearing and heavy earth moving started |
| September 2008 - present | Active mine construction |
| July 2009 | $235 Million Debt Financing |
| December 2009 | Mills delivered |
| February 2010 | Debt replaced by Equity Construction 50% complete |